INSTALLATION MANUAL

STEP 1: PAGE 2 OF 2:

JOB SITE PREPARATION REMINDERS

    WOOD FOUNDATIONS OR DECKS

When securing Bottom tracts to an existing deck or wood foundation, make sure the counter flashing goes under the entire Bottom Track and overlaps down on to the outside of the deck. There are no sealants that will bond aluminum to wood, so make sure the flashing is sealed to the bottom of the Bottom Track with Silicone.

MATERIAL DELIVERY AND SITE PREPARATION

DIAGRAM 1.
step1-2o22.gif (8978 bytes)

DIAGRAM 1.

When the materials have been delivered to the job site, the first step is to lay out all like materials together.This is done to inventory all the material for the installation and to be able to select only the material needed for each step. The layout sheet and the cut list will help in the inventory process.

The material should be placed outside the perimeter of the room being built. All windows panels and screens should be removed from modules during this step.